Despite global travel restrictions and supply bottlenecks during the Covid-19 pandemic, we managed to successfully commission a new production plant. With the help of our specially developed solution framework CROME (Concept, Readiness Check, Open Points, Mobilization, Execution), we implemented a holistic commissioning concept that ranged from strategy and preparation to operational implementation on site.

Background

The Covid-19 pandemic led to the interruption of the assembly phase of a greenfield production plant. After a six-month shutdown, the plant had to be completed despite existing travel restrictions. This extraordinary situation required innovative commissioning solutions involving engineers, suppliers and third-party providers worldwide.

Specific Task

Our task included setting up a holistic commissioning concept, coordinating and implementing supplier integration and supporting the adaptation of framework agreements, work instructions and processes. The aim was to finalize the commissioning of the plant on time and on budget despite the challenges posed by the pandemic.

KBC Solution Approach

We developed a comprehensive remote commissioning concept based on our CROME framework (Concept, Readiness Check, Open Points, Mobilization, Execution). This included the virtual integration of over 15 suppliers, from the initial approach to the operational commissioning. We adapted framework contracts, work instructions and processes to the new circumstances in close coordination with technology experts and suppliers. Our approach enabled the virtual commissioning to be carried out safely without any accidents or incidents.

Weibliche Person, blonde lange Haare, blaue Augen, lächelnd, trägt eine weiße Bluse und schwarze Hose, stehend mit beiden Händen an der Hüfte abstützend
Weibliche Person, blonde lange Haare, blaue Augen, lächelnd, trägt eine weiße Bluse und schwarze Hose, stehend mit beiden Händen an der Hüfte abstützend
Nadia Massari
Manager

Achieved Effect

The commissioning of the production plant was successfully completed with 100% target achievement in terms of adherence to schedule and budget. We ensured the support and maintenance of the warranty on the part of the suppliers. By avoiding travel, we were able to reduce the project’s carbon footprint. The successful completion under these challenging conditions strengthened the entrepreneurial spirit throughout the project team. Overall, the project demonstrated the ability to implement innovative solutions and successfully complete complex projects even under extreme conditions.